Master data
Every feed contains:
- EAN
- channel
- unit (kWh or m3)
- start of the period
- end of the period
Once Meterbeheer has looked up the connection at the grid operator (by default for EDSN, after a Smart Meter Check for other metering services), the feed also contains:
- connection type (small or large consumption)
- grid operator
- installation date of the current meter
- authorization start date (historical data is available from that date)
- authorization end date
API+ adds:
- whether a smart meter is installed
- whether it can be read remotely
- the event the supply contract started with
EDSN error codes
When an EDSN connection gets no metering data, EDSN returns an error code. The code is shown in the Meterbeheer dashboard. Without API+, the feed has one line saying why no data is coming in. With API+, the feed has a list with the code and date per refused day.
| Code | Description | Action by | Explanation |
|---|---|---|---|
| 006 | The EAN connection is unknown. | Customer | Enter the correct combination of EAN, postal code and house number. |
| 007 | No smart meter on the EAN connection. | Connection owner | Request a smart meter from the grid operator. |
| 008 | The requesting party is not authorized. | Customer | Add the authorization for this EAN with the correct date. |
| 009 | No metering data available, the smart meter is in the deployment phase. | Connection owner or grid operator | The grid operator has to activate the smart meter. |
| 010 | The date of the requested data is in the future. | None | No action needed. |
| 011 | The date of the requested data is too old, the meter readings are no longer available. | None | No action needed; the data of this day can no longer be requested. |
| 012 | Requested metering data not available, meter temporarily out of order. | Grid operator | The grid operator has to resolve the fault. |
| 013 | The meter cannot carry out this specific request. | None | No action needed. |
| 014 | Requested metering data not available, the fault is known and being handled. | Grid operator | The grid operator has to resolve the fault. |
| 038 | The smart meter is administratively switched off. | Connection owner | The owner of the connection has to give the grid operator permission to read the meter remotely. |
| 039 | The smart meter installed cannot technically be read remotely. | Connection owner | The smart meter has to be replaced. |
| 040 | The requesting party is no longer authorized, because the contract holder of the connection has changed. | Customer | Have the new contract holder sign a new authorization. |
| 041 | Requested metering data not available, large-scale outage. | Grid operator | The grid operator has to resolve the fault. |